Carbon Emissions
65 lbs/sf-yr
0
Net zero
170
Average building

Note: The graph below shows data submitted by the project team and has not undergone a third-party review.

<b>SB 2030 Standard</b><br>51 pounds CO2e/sf/year <b>As Designed</b><br>65.31 pounds CO2e/sf/year
The greenhouse gas emissions associated with the project’s annual energy use are calculated in pounds of carbon dioxide equivalents per square foot per year (lbs CO2e/sf/year). It shows the project-specific SB 2030 Carbon Standard, the predicted carbon emissions from the fuel mixture specified in the project’s energy model, and the actual annual carbon emissions calculated from meter readings (if available).
Energy Strategies
Domestic Hot Water
  • Recirculating Hot Water Pump
Envelope / Insulation
  • Glazing with SHGC Under 0.4
  • R-20 to R-30 Wall Insulation (for Opaque Walls)
  • R-50 to R-60 Roof Insulation
  • Shades or Overhangs
  • Window / Glazing U-Factor under 0.25
HVAC
  • Economizer
  • Energy Recovery System (Including Heat Recovery)
  • High Efficiency Fans
  • Variable Speed Drives
Lighting
  • Continuous Daylighting Controls
  • LED Lighting
  • Occupancy or Vacancy Sensors
  • Optimized Emergency Lighting
  • Provide Daylighting Through Side Windows
  • Reduced Lighting Power Density
  • Stepped Daylighting Controls
Metering
  • Dedicated Plug Load Electric Panel
  • Smart Meters
Operations
  • Operations Manual Created for Project
Power Management
  • Load Sensors
  • Power Management Policy
Daylighting
  • 85% or Greater of Continually Occupied Space is Daylit.
Occupant Control
  • Occupant Daylighting / Glare Control
  • Occupant Electric Lighting Control
Ventilation
  • Ventilation Compliant with ASHRAE 62
Design
  • Reuse Existing Building

<< Back to Case Studies Home

 B3 HomeB3 Home

 GuidelinesGuidelines

 SB 2030 Energy StandardSB 2030 Energy Standard

 BenchmarkingBenchmarking

 Energy Efficient OperationsEnergy Efficient Operations

 Post Occupancy EvaluationPost Occupancy Evaluation

Sponsors

Project Team

Case Studies Database

Admin Login

B3 Case Studies v4.1.0.4035